MSA November Construction Update

    Beautiful morning at MSA Professional services. Steel erection is now complete, cold form stud framing is almost done with interior stud work being done starting next week and MEP Rough-Ins starting in about three weeks! Lots of great progress happening here!

    Sullivan designBUILD // November, 16 2018

    Albion Salt Storage Building

    In March 2019 we started construction on a nearly 14,000 sqft 10,000 ton salt storage building for the Town of Albion through the Dane County Department of Public Works, Hwy & Transp. This project is located in Edgerton, WI and is expected to finish this summer.
    Go to Post
    Sullivan designBUILD // May, 24 2019

    Wisconsin Kenworth (CSM Companies) May Update

    Lots of progress happening at Wisconsin Kenworth! The footings and foundation were just completed with underground electrical and plumbing work to start in the parking lot and within the building area.
    Go to Post
    Sullivan designBUILD // May, 20 2019